CfD output, actual and projected

Generation from CfD-supported projects in GWh, by nation, by technology and by auction round, with actual metered output followed by a projection.

Projected output is each project’s expected start date × contracted capacity × assumed load factor. Terminated contracts are excluded. Every breakdown sums to the same UK total, so switching between them changes the slice and not the bottom line.

Figures can be read as GWh or as a share of the UK CfD total for that year, and every filter on the site — nation, technology, status, project name — narrows the tables.

612 CfD contracts are in the register: 88 operational, 473 not yet generating and 51 terminated. The 561 live contracts hold 49.8 GW of contracted capacity across 12 technologies and allocation rounds AR1, AR2, AR3, AR4, AR5, AR6, AR7, BC, IC. Settlement data runs to 6 August 2026.

Load factor assumptions are set out on Load Factors; per-project output is in the projects table.